The library board received an update from Project Coordinator Kate Smith at Monday's board meeting, and here's what's happening with the new library project:
A few items, such as masonry, roofing, siding, and fascia are on hold until the weather warms up. Installation of plumbing, heating/air conditioning, and electrical are progressing. In the next month, contractors plan to work on windows, drywall work will continue, and roofing and masonry will progress if the weather allows.
Construction is just over 60% complete!