Here are the latest updates on the new building project:
*The drywall is up, but not finished. It will take 3-4 weeks to do the finish work, then the walls will be ready for paint.
*The metal roof is being installed on the south side of the building, but the colder temperatures may put this on hold.
*Heating/AC work continues.
*All of the exterior windows have been installed except the 9 high ones on the south side of the building.
I'm also including a picture taken by Roger Kirkwood in early January of the brickwork that's been done on the back exterior of the building.