Kate Smith, Project Coordinator, shared the latest progress on the new library building at the October 12 board meeting. Roof trusses have gone up, as you can see in the picture below. Metal stud framing was scheduled to begin the first part of October. Exterior masonry materials are also being ordered. During the month of October, the focus is on finishing the parking paving and working on wall framing, trusses, sheathing, insulation, etc. to get the building enclosed before winter.
I took the following pictures today, Monday, October 19th.