Thursday, February 11, 2010

Latest update

A few staff members visited the building site today, and it sounds like taping, mudding, and sanding of the drywall is taking place now. Below, a few staff members check out their future work room!




At Monday's board meeting, Kate Smith, project coordinator, reported that building construction is just over 70% complete. Even though that seems like completion is near, there are still plenty of things to do before the library is ready to open. Kate reported that within the next month, we can expect painting of the walls to begin, and work on the ceiling to start. Measurements for woodwork such as chair rail and trim should take place this month also. Last week, a group of staff and a trustee visited Stocks in Champaign, along with a designer from Apace Design to look at and try numerous pieces of furniture. This visit helped us determine what furnishings will best meet our needs and the comfort of our patrons in the new building.

Monday, February 8, 2010

Drywall is up!

This video contains pictures taken January 29, 2010. You can really visualize what the inside of the building will look like (minus shelves, furniture, etc...)

Monday, February 1, 2010

Windows!

This picture was taken today, and you can see windows if you look to the right side of the picture. Also check out the green metal roofing material that's been installed on the upper portion of the roof. More updates to come soon!